Work Session - 9/13/17


Recently we had a couple of trains that derailed when backing into the Ochard Yard, so Ron Trenhaile, Dick Scott and Frank Foti checked out the switch points. They replaced a couple of ties and added shims to the point rail.
With points shimmed, Dick got a wheelborrow of ballast and dumped it as Ron tamped the ballaast between the ties. Frank and Ron checked the gauge and refastened the rail to bring it up to specs.
After running a train through, Dick and John Reba took on the task of bending the switch point so a wheel flange wouldn't pick the switch point. Dick Clark is checking the rail gauge through the switch points.
The crew next moved over to Thorn to work on the by-pass track we are installing where John Koontz looks over the rail crossing site. Dick Clark removes the bolts at the rail joints as John watches.
We'll take the existing track section out of operation so we can place the by-pass track down and make the crossing later. John, Dennis Crislip and Paul Zorko look on as Dick continues removing the eight bolts at the tie joints.
Wouldn't you know it, there is an old tree stump right in the middle of the right-a-way of the by-pass track that has to be chopped out. John using a maddock worked on removing the stump.
A picture of Dick just relaxing after he had taken the rail joiners off the track panel so we could remove the panel. John completes the task and takes a breather, you can see the stump pieces lying around.
With that done we placed and fastened down another track panel. The crew work installing another panel beyond the crossing area.
                                               